Town Capital Improvement Projects

Print
Press Enter to show all options, press Tab go to next option

Construction Projects

 


Envision DPR - Western Segment Utility Undergrounding Project Area image

Envision DPR (Donner Pass Road) Western Segment Utility Undergrounding Project (C1815)

Description: Convert overhead utilities to underground facilities along Donner Pass Road.
Status: Infrastructure Constructed - Summer of 2018. The overhead lines and power poles will be removed Summer of 2019.
Budget: $3.9 million
Funding: General Fund and Utility Partnership.
Project Manager: Scott Mathot


Envision DPR Phase 1 aerial image

Envision DPR (Donner Pass Road) Corridor Improvement Project Western Segment Phase 1 (C1407)

Description: Construct sidewalk and pedestrian crossing enhancements along Donner Pass Road between Richards Boulevard and State Route 89 South/Frates Lane. 
Status: Currently in progress. 
Budget: $6.9 million 
Funding: Federal ($1.5 million), Regional Surface Transportation Program, Local (Measure V), and General Fund 
Project Manager: Scott Mathot

 


Image Stockrest Springs_Truckee Way_East Jibboom St Roundabout Design 

Stockrest Springs/Truckee Way/East Jibboom St Roundabout (C1612)

Description:  Construct a single-lane roundabout at the intersection of Truckee Way, Stockrest Springs, and East Jibboom Street. Work would likely include a pedestrian connection across I-80 as well as new street light installation, landscaping and transit shelter. The intersection provides access to the Town’s Public Service Center and United States Forest Service offices to the east; and a mixed use development that includes a 114-room hotel and 138 rental residential units (currently under construction) to the west. 
Status:  Currently in progress.
Budget:  $3.8 million 
Funding:  General Fund, General Fund Housing Designation, Measure V and Developer Funding 
Project Manager:  Todd Landry


Image - Public Service Garages conceptual elevations


 

 

 

 

 

 

Public Service Center Garages Project (C1609)

Description: Update the design and construct new Public Works Street Maintenance garages, Public Works Facilities maintenance building, and Police evidence storage building on the Public Service Center property.
Status: Construction currently in progress.
Budget: $12 million
Funding: General Fund, Financing, Facilities and Police Department  Fees.
Project Manager: Scott Mathot


 Paving and Drainage Project

2019 Slurry Seal Project (C1901)

Description: Slurry Seal streets in Tahoe Donner, Glenshire, Old Greenwood, and Donner Lake.
Status: Work is anticipated to begin in August or September of 2019.
Budget: $1,144,000 million 
Funding: Local (SB1 Road Maintenance and Rehabilitation Account Funds, Measure V, Truckee Special Service Area #1, and Truckee Special Service Area #5). 
Project Manager: Mike Vaughan

 


Coldstream Road - Donner Creek Structure Replacement Project  (C1607)

Description: Replace the aging  culvert under Coldstream Road with a new arch culvert across Donner Creek to increase flood capacity and improve fish passage. 
Status: Construction anticipated in 2020. 
Budget: $2.3 million 
Funding: Measure V, AB1600 Traffic Fees, General Fund, and Developer Funding. 
Project Manager: Mike Vaughan

 


 Aerial image of Northwoods Blvd. & Donner Pass Road Intersection

Northwoods Boulevard/Donner Pass Road Roundabout Project (C1608)

Construction: Construct a roundabout at the intersection of Northwoods Boulevard and Donner Pass Road. 
Status: Currently in the design phase with construction anticipated in 2020. 
Budget: $3.7 million 
Funding: General Fund 
Project Manager: Scott Mathot


 Church Street Extension Draft Plan Alternative image

Church Street Extension Project (C1804) & Trout Creek Restoration - Reach 4 and Upper Reach 5 (C1705)

Link to Initial Study/ Mitigated Negative Declaration document.

Description: Planning, design, and construction of a new eastern extension of Church Street roadway to connect Church Street between the Railyard Development to a new intersection with Glenshire Drive just west of the Rock and Rose. The Project includes a new bridge over Trout Creek with restoration to a portion of the creek upstream and downstream of the new bridge. The new intersection with Glenshire Drive would be configured as a roundabout.  The Trout Creek Restoration Project would restore Trout Creek upstream of the new bridge to upstream of the balloon track.  The restored creek would provide 100 year flood protection and improve aquatic plus riparian habitat.  Both projects would occur concurrently.
Status: Preliminary planning and a  30% level design was completed in July 2018. A second design phase has started and will refine the design plans from the 30% design level to 100% (final design) level likely occurring before May of 2021 and would include environmental permitting and preparation of construction plans, specifications, and cost estimates. Staff is currently applying for stream restoration grant funds to cover the construction cost of the steam restoration work. 
Budget/Funding: Approximately $7.7 Million in AB 1600 Traffic Impact Fee and Facilities Impact Fee funds. 
Construction: Tentatively planned for the 2021 Construction Season.
Project Manager: Todd E. Landry


 Small Town Logo

I-80/ Donner Pass Road/ Coldstream Road Roundabout Project (C1712) 

Description: Construct a single-lane roundabout at the intersection of I-80, Donner Pass Road, and Coldstream Road.
Budget: $3.9 million
Funding: AB1600 Traffic Impact Fees, AHSC Program Funds, and Developer Funding.
Project Manager: Mike Vaughan

 


West River Street Streetscape Project (C1703)

Description: The project will include sidewalks, curbs, gutters, crosswalks, ADA accessibility, landscaping, lighting, utility undergrounding, storm drainage improvements, and parking improvements.
Status: 
Town staff and the consultant team are working with property owners and businesses in the area to develop the design.
Budget:
$5 million
Funding:
General Fund, AHSC Grant, Streetscape Designation.
Project Manager: 
Jessica Thompson


bridgeFinal

 

 

 

 

 

 

Reimagine Bridge Street

Description: The project will consist of intersection improvements for pedestrians and vehicles on Bridge Street between Donner Pass Road and East and West River Street.
Status: Currently in the design phase.
Budget: $4.4 Million 
Funding: AB 1600 Traffic Impact Fees.
Project Manager: Jessica Thompson 


Truckee River Legacy Trail Phs 4 Project Aerial image

Truckee River Legacy Trail Phase 4 (C0702)

Construction: Class 1 asphalt trail between Brockway Road and West River Street/89 South intersection.
Status: Currently in the design phase. 
Budget: $11 Million 
Funding: Measure R, Unfunded 
Project Manager: Jessica Thompson  


For information about completed projects, please click here.  

If you have any questions, please contact a staff member.

 

2019 Engineering Capital Improvement Projects (approximate location only)