Town Capital Improvement Projects

Print
Press Enter to show all options, press Tab go to next option

In Progress

 

Envision DPR - Western Segment Utility Undergrounding Project Area image

Envision DPR (Donner Pass Road) Western Segment Utility Undergrounding Project (C1815)

Description: Convert overhead utilities to underground facilities along Donner Pass Road.
Status: Construction scheduled for Summer of 2018.
Budget: $2.8 million
Funding: General Fund and Utility Partnership.
Project Manager: Scott Mathot


  Small Town Logo

 

Coldstream Road and Donner Creek Crossing Structure Replacement (C1607)

Description: Replace the aging box culvert under Coldstream Road with a new bridge across Donner Creek to increase flood capacity and improve fish passage. 
Status: Construction anticipated in 2019. 
Budget: $1.2 million 
Funding: Measure V, AB1600 Traffic Fees, General Fund, and Developer Funding. 
Project Manager: Mike Vaughan


Church Street Extension Draft Plan Alternative image 

Church Street Extension Project (C1804)

Description: Planning, design, and construction of a new eastern section of Church Street roadway to be extended from the balloon track in the Railyard Redevelopment area to a new intersection with Glenshire Drive just west of the Rock and Rose. The Project includes a new bridge over Trout Creek with restoration to a portion of the creek upstream and downstream of the new bridge. The new intersection with Glenshire Drive would be configured as a roundabout. 
Status: Preliminary planning and a  30% level design was completed in July 2018. A second design phase would refine the design plans from the 30% design level to 100% (final design) level likely occurring between September 2018 and June 2019 and would include environmental permitting and preparation of construction plans, specifications, and cost estimates. The start of Phase 2 design is contingent upon the Public Utility Commission granting approval for the roadway to cross the balloon track. 
Budget/Funding: Approximately $4.5 Million in AB 1600 Traffic Impact Fee and Facilities Impact Fee funds. 
Construction: Tentatively planned for the Summer/Fall of 2019. 
Project Manager: Todd E. Landry


In Design

Envision DPR Phase 1 aerial image

Envision DPR (Donner Pass Road) Corridor Improvement Project Western Segment Phase 1 (C1407)

Description: Construct sidewalk and pedestrian crossing enhancements along Donner Pass Road between Richards Boulevard and State Route 89 South/Frates Lane. 
Status: Currently in the design phase with construction Summer of 2019. 
Budget: $5 million 
Funding: Federal ($1.5 million), Regional Surface Transportation Program, Local (Measure V), and General Fund 
Project Manager: Scott Mathot

 


Aerial image of Northwoods Blvd. & Donner Pass Road Intersection

Northwoods Boulevard/Donner Pass Road Roundabout Project (C1608)

Construction: Construct a roundabout at the intersection of Northwoods Boulevard and Donner Pass Road. 
Status: Currently in the design phase with construction anticipated in 2020. 
Budget: $2.3 million 
Funding: General Fund 
Project Manager: Scott Mathot

 


West River Street Streetscape Project

Description: The project will include sidewalks, curbs, gutters, crosswalks, ADA accessibility, landscaping, lighting, utility undergrounding, storm drainage improvements, and parking improvements.
Status: 
Town staff and the consultant team are working with property owners and businesses in the area to develop the design.
Budget:
Funding:
Project Manager: 
Jessica Thompson


Bridge Street,West River Street and Donner Pass Road Intersection Improvements aerial image

Reimagine Bridge Street

Description: The project will consist of intersection improvements for pedestrians and vehicles on Bridge Street between Donner Pass Road and East and West River Street.
Status: Currently in the design phase.
Budget: $2.4 Million 
Funding: AB 1600 Traffic Impact Fees 
Project Manager: Jessica Thompson 

 


 

Truckee River Legacy Trail Phs 4 Project Aerial image

Truckee River Legacy Trail Phase 4 (C0702)

Construction: Class 1 asphalt trail between Brockway Road and West River Street/89 South intersection.
Status: Currently in the design phase. 
Budget: $11 Million 
Funding: Measure R, Unfunded 
Project Manager: Jessica Thompson 


Image - Public Service Garages conceptual elevations

 

 

 

 

 

 

 

Public Service Center Garages Project (C1609)

Description: Update the design and construct new Public Works Street Maintenance garages, Public Works facilities maintenance building, and Police evidence storage building on the Public Service Center property.
Status: Design work to be completed Summer 2018, Construction to begin late Summer/Fall 2019.
Budget: $7 million
Funding: General Fund
Project Manager: Drew Jack and Bret Albert


For information about completed projects please click here.  

If you have any questions please contact a staff member.