Capital Improvement Projects Status

  

Anticipated 2017/2018 Construction Projects


2017 Slurry Seal Project (CIP C1701)

Description: Slurry seal streets in the Tahoe Donner, Glenshire, Prosser Heights, Olympic Heights, and Downtown Subdivisions.
Status: Construction is anticipated to be complete in September 2017.  Once construction begins, schedules will be posted on the Town's website.
Budget = $845,000
Funding: Local (Measure V, Truckee Special Service Area #1, and Truckee Special Service Area #5)
Project Manager: Mike Vaughan
Slurry Seal Map 2017

 

2016 Paving and Drainage Project (CIP C1602­)

Description: Pave portions of Northwoods Boulevard, Fjord Road, Alder Creek Road, Glenshire Drive, Dorchester Drive, and Donner Pass Road, as well as, drainage improvements at various locations throughout town.
Status: Construction to be completed in Summer of 2017.
Budget: $5,200,000
Funding: Local (Measure V, Overlay Designation, Truckee Special Service Area #1 funds and Truckee Special Services Area #5 funds)
Project Manager: Mike Vaughan

2016_Paving_Drainage_Overview


2016 Recessed Striping and Marking Project (CIP C1603)

Description: Replace existing roadway striping and pavement markings (crosswalks) with recessed thermoplastic.
Status: Construction anticipated for Summer of 2017.
Budget: $230,000
Funding: Local (Measure V funds)
Project Manager: Mike Vaughan

 


Glenshire Drive/Dorchester Drive Paving and Widening Project (CIP C1605)

Description: Reconstruct and widen Glenshire Drive (Truckee River Legacy Trail to Dorchester Drive) and Dorchester Drive (Glenshire Drive to Waterloo Circle). This project also includes a left-turn lane on Glenshire Drive at Dorchester Drive. Project will also include a pedestrian crossing of Glenshire Drive in the vicinity of the Legacy Trail Trailhead.
Status: Planning and design began in late 2016, construction is anticipated to begin Summer of 2017.
Budget: $2,900,000
Funding: ATP Grant, AB 1600 Traffic Impact Fee, TSSA #5 Glenshire Funds and Measure V
Project Manager: Todd Landry

Glenshire_Exhibit2

  

Envision DPR (Donner Pass Road) Corridor Improvement Plan (C1504)

Description: Planning and design of streetscape improvements on Donner Pass Road between Coldstream Road and McIver Roundabout. Initial phase would develop a conceptual layout for pedestrian safety improvements integrated with the corridor streetscape design. 
Status: Design and planning currently in process.
Budget: $600,000
Funding: Federal, AB 1600 Traffic Impact Fees and Measure V
Project Manager: Scott Mathot

Please visit: www.EnvisionDPR.com for more information.

  


Envision DPR (Donner Pass Road) Corridor Improvement Project
Western Segment Phase 1 (CIP C1407)

 

DPR Corridor Improvements

Description: Construct sidewalk and pedestrian crossing enhancements along Donner Pass Road between Richards Boulevard and SR 89 South/Frates Lane.
Status: Currently in the design phase with construction anticipated in 2018.
Budget: $3.65 million
Funding: Federal ($1.5 million), RSTP, Local (Measure V), and General Fund
Project Manager: Scott Mathot

Please visit: www.EnvisionDPR.com for more information.

 

 

   


Brockway Road Corridor Improvement Project (CIP C1604) 

 Description: Reconstruct and widen Brockway Road from Estates Drive to SR 267.  Project also includes a left-turn lane at Reynolds Way, widening for Class II bike lanes, installation of pedestrian crossing enhancements, and construction of landscape medians.
Status: Currently in the planning and design phase with a potential construction start date of 2017.
Project Manager: Jessica Thompson

 BrockwayRoad_Overview_AttachA

 

 
For more information about completed projects please click here.


If you have any questions please contact a staff member.

Becky Bucar (530) 582-2932, bbucar@townoftruckee.com

Todd Landry (530) 582-2904, tlandry@townoftruckee.com

Jessica Thompson (530) 582-2938, jthompson@townoftruckee.com

Mike Vaughan (530) 582-2923, mvaughan@townoftruckee.com

Sarah Kunnen (530) 582-2931, skunnen@townoftruckee.com 

Scott Mathot (530) 582-2481, smathot@townoftruckee.com

Drew Jack (530) 582-2483, djack@townoftruckee.com

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer